  • Concept Design

    January 2022

     

    -

     

    April 2022

    In early 2022 Stroud District Council appointed a team of consultants to review the potential for improvements to Wallbridge. Initial site visits and design team workshops were carried out to understand the local context and any constraints such as the adjacent road network. The historical significance of Wallbridge has been fully appreciated. In particular the canal and the former Stroud Brewery. As well as the strategic location as a gateway to Stroud town centre. During this early period we consulted with local representatives and their input has helped to inform the concept masterplan.
  • Public Consultation

    May 2022

     

    -

     

    June 2022

    During May we would like to gain feedback on the Concept Masterplan from those who are directly affected by the Wallbridge area as well as those who might benefit from the proposed landscape in the future. A public drop in session will take place at Wallbridge on the 20th May 3pm until 7pm and the 21st May 9am until 1pm. Please refer to our Latest News page for further information.
  • Scheme Design

    June 2022

     

    -

     

    Upcoming

    Following the public consultation period we will collate the findings to ensure any stakeholder concerns, requirements and aspirations inform the masterplan.
  • Levelling Up Fund Submission

    July 2022

     

    -

     

    Upcoming

    The full scheme design and masterplan will be submitted in early July 2022.